CALDICOT & WENTLOOGE LEVELS INTERNAL DRAINAGE BOARD

Audit of Accounts 2010-11 – Report in the Public Interest

 

Review of progress with the Board’s response to the findings of the Report

 

 

 

 

 

 

 

 

 

 

 

Control Objective 1: Governance

Ref

Weakness identified in PIR

PIR comment

Agreed management action to address weakness

Date

Responsible Officer

17 – 24

 

 

 

 

 

 

 

 

 

 

25 – 35

 

 

 

 

 

 

 

 

36 – 48

The Drainage Board’s governance arrangements were inadequate and ineffective.

 

 

 

 

 

 

 

 

The Drainage Board’s decision-making framework was not properly constituted and, as a result, the Drainage Board has been operating contrary to the law.

 

 

 

 

 

The Drainage Board’s Establishment Committee did not have a clear membership and remit, and inadequate records were kept of its proceedings prior to 2011.

 

Public bodies must demonstrate that they are delivering the services for which they are responsible in accordance with principles of good governance. This means that public bodies must put in place robust arrangements

 

 

 

The Drainage Board is a statutory body and must act in accordance with legislation that governs its operations.

 

 

 

 

 

Appointments to & membership of the Board’s Establishment was unclear

 

The records of the proceedings of meetings of the Establishment Committee prior to 2011 were inadequate

 

Key strategic documentation currently being produced:

Strategic plan, operational plan, organisational budget, work programme,

Private works policy, which links to the overall agreed work programme

 

 

Governance documents currently being revised for adoption – delay due to NCC not appointing representatives until December 2012. WG Ministerial approval will be sought in January 2013 once adopted by Board.

 

No committee structure in place since July 2011. The Board has established a Capital Expenditure Working Group to make recommendations to the Board about major items of capital expenditure

Jan 2013 and will continue to be developed

 

 

Spring 2013

             

Achieved

Rules approved by WG  Minister on 13/02/2013

 

 

Achieved

General Manager

 

 

 

General Manager

Board Engineer

F&SSM

                                        General Manager

F&SSM

 

 

                                         

                                                Board Engineer

F&SSM

 



 

 

 

Control Objective 1: Governance

Ref

Weakness identified in PIR

PIR comment

Agreed management action to address weakness

Date

Responsible Officer

 

49 – 55

 

 

 

 

 

 

 

 

 

 

56 – 67

 

 

 

 

 

 

 

 

 

The formal records of committee and Board proceedings contain inaccuracies, anomalies, breaches of information law and, in a number of cases, minutes appear to have been drafted to represent the views of the former Clerk and Engineer and former Office and Personnel Manager

 

 

 

 

The Board’s failure to introduce key governance policies and procedures has contributed to major governance failings within the Drainage Board’s operations.

 

The record of proceedings for meetings of a public body is extremely important in demonstrating that the body has operated in a lawful, fair and transparent way and made its decisions objectively.

 

 

 

 

Public bodies should establish robust and effective governance arrangements which set out the parameters within which the organisation operates and which help direct and guide the behaviour of members of staff and Board Members.

 

 

 

Improvements were put in place in July 2012 for the recording of proceedings for meetings.  Since Oct 2012 the Board has engaged the services of Peter Evans, Head of Democratic Services MCC, to take the minutes of future Board meetings in order to demonstrate a further measure of independence.

 

 

Governance documents currently being revised for adoption – delay due to NCC not appointing representatives until December 2012. WG Ministerial approval will be sought in January 2013 once adopted by Board.

 

 

 

Achieved

 

 

 

 

 

 

Achieved

Suite of amended governance documents received at Board meeting  11/02/2013 further amended documents  approved at Board  meeting  18/03/2013

 

General Manager

 

 

 

 

 

General Manager

F&SSM


                                                                                                                                       

 

 


 

 

Control Objective 2: Members & Officers

Ref

Weakness identified in PIR

PIR comment

Agreed management action to address weakness

Date

Responsible Officer

68 - 123

Some members and officers acted in a way which is likely to undermine public confidence in the way in which the Drainage Board operated.

 

 

 

 

 

 

The standards expected of those holding public office are high. It is essential that such individuals conduct themselves in accordance with the seven principles of public life the so-called ‘Nolan principles’.

 

The former Clerk & Engineer had a conflict of interest when he drew up proposals for his own redundancy package and presented those proposals to the Board’s Establishment Committee.

The Board failed to put in place arrangements to ensure the independent review of the former Clerk & Engineer. The Clerk & Engineer was involved in submitting proposals relating to his pay to committees of the

Board

 

 

 

Appropriate changes  in the way such issues are handled by the Board are now in place to ensure there is no repetition of such action by either Board members or Board employees

 

 

 

 

 

 

Achieved

General Manager

F&SSM



 

 

Control Objective 2: Members & Officers

Ref

Weakness identified in PIR

PIR comment

Agreed management action to address weakness

Date

Responsible Officer

 

124 – 158

 

 

 

 

 

 

 

 

Three members of the Board and the former Clerk & Engineer participated in proceedings of the Board relating to an ongoing case when they had a conflict of interest in the matter.

 

 

 

Three members of the Board participated in proceedings on several occasions of the Board relating to the sea defences case when they had disqualifying personal interests.

 

 

 

All Board members are fully aware that it is their responsibility to register any relevant interests and to declare such interests in relation to the proceedings of the Board.  A Register of Interests is kept and all declaration of interest is recorded.

 

Achieved

 

Revised Register Of Interest declaration circulated to Board members for completion 08/04/2013

 

General Manager and all Board Members


 

Control Objective 3: Budget

Ref

Weakness identified in PIR

PIR comment

Agreed management action to address weakness

         Date

Responsible Officer

159 -

The Drainage Board did not exercise good financial management and control at corporate level

The Drainage Board’s budget setting process for 2010-11 was not robust and Board minutes do not record that the Board formally approved the budget or amendments to it.

 

 

 

 

 

 

 

 

 

The Drainage Board did not have a formal budgetary control system in place for financial years prior to 2011-12 and had no documented financial control procedures.

 

 

 

 

 

 

 

 

 

 

 

The way in which the Board has set the annual rate has resulted in a potential inequity between the respective financial burdens placed on the taxpayer and the local ratepayer. Furthermore, the Drainage Board is unable to demonstrate that it has been setting a lawful rate for several years.

Improvements have been put in place for producing the 2013/2014 budget.  A work programme and operational plan will be produced and responsible delegated budget holders.

 

 

NCC the Board’s internal auditors carried out  an audit of Budgetary control systems  in August 2012

 

 

 

 

Procedures now in place

 

 

 

 

 

 

 

 

The necessary information required to demonstrate the Board is setting a lawful rate has not yet been obtained as the information is not readily available from local authorities or the Wales Valuation Office in the format requested by the F&SSM

 

Achieved

A more detailed work programme to be produced for 2013/2014

 

Implementation of recommendations

In producing 2013/2014 budgets.

 

 

 

Achieved

                                

 

 

 

 

 

 

 

Local authorities unable to provide information requested.  A further meeting to be arranged with WAO to discuss way forward.

 

 

F&SSM and all budget holders.

 

 

 

 

 

 

F&SSM and all budget holders.

 

 

 

 

F&SSM

 

 

  

 

 

 

 

 

F&SSM                               

                                                               


 

 

 

 

 

 

 

 

 

 

 

 

 

 

Control Objective 1: Taxpayer’s Money

Ref

Weakness identified in PIR

PIR comment

Agreed management action to address weakness

Date

Responsible Officer

 

179 – 180

 

 

 

 

 

 

 

 

 

181 – 198

 

 

 

 

 

 

 

 

 

199 – 228

 

 

The Drainage Board has failed to demonstrate that it has achieved value for money and acted lawfully in some key areas.

 

 

 

 

 

 

The Drainage Board spent taxpayer’s money funding ‘inspection’ visits by Board Members and officers without having any business case to justify these visits or any effective means of assessing the benefits realised from thee visits. The expenditure did not represent value for money and the expenditure was contrary to law.

 

 

The Drainage Board did not have adequate procedures in place for the procurement of goods and services, and did not always comply with its own procedures. As a result, the Drainage Board is unable to demonstrate that it has achieved good value for money from their purchases

 

Public bodies are funded by taxpayers. It is therefore imperative that they use the resources that they have at their disposal in an economic, efficient and effective way. They should be able to demonstrate value for money.

 

 

The Drainage Board failed to demonstrate that it achieved value for money in respect of its inspection trip to Italy, Northern Ireland & the Netherlands.

 

 

 

 

 

When purchasing equipment, public bodies must ensure that they can demonstrate that procurement complies with proper procedure and that value for money has been secured.

 

The Board acknowledges that there is a need to demonstrate that its resources are being used in an economic, efficient and effective way and that it needs to demonstrate VFM. The General Manage is considering ways in which the Board’s activities can be better scrutinised

 

There have been no further ‘inspection visits’ and any such visits will only be organised in the future if a robust business case can be demonstrated

 

 

 

 

 

Appropriate procurement procedures have been put in place to ensure VFM from purchases.

 

On going

 

 

 

 

 

 

 

 

 

Achieved

 

 

 

 

 

 

 

 

 

Achieved

 

General Manager

 

 

 

 

 

 

 

 

 

General Manager

 

 

 

 

 

 

 

 

 

Board Engineer

F&SSM


 

 

 

 

 

Control Objective 1: Taxpayer’s Money

Ref

Weakness identified in PIR

PIR comment

Agreed management action to address weakness

Date

Responsible Officer

229 - 234

On some occasions, the Drainage Board used public resources in supporting external organisations which it had no statutory powers to do so

The Drainage Board is a statutory body. It is only able to act in accordance with the statutory powers granted to it. It cannot use public resources to undertake any activities which are outside its legal remit.

A review of the external organisations supported by the Board was carried out last year and the Board now only supports appropriate external bodies in line with its legal remit

Achieved

General Manager

 

 

 

 

 

 

 

 

 

 


 

 

 

Control Objective 1: HR Policies & Procedures

Ref

Weakness identified in PIR

PIR comment

Agreed management action to address weakness

Date

Responsible Officer

235 – 242

 

 

 

 

 

 

 

 

 

 

 

243 – 246

 

 

 

 

 

 

 

 

 

The Drainage Board did not have HR policies and procedures in place. This has led to a lack of transparency over the grading and remuneration of staff. Furthermore, the former Clerk and Engineer recommended to the Board that the Office and Personnel Manager’s post be re-graded even though he had a personal and pecuniary interest.

 

 

 

 

The decisions taken to allow senior staff time off in lieu of extra-contractual hours worked were not taken properly.

Internal drainage boards may remunerate their staff as they see fit as long as this is within reasonable limits and is transparent.

 

It is incumbent on each board to develop effective HR policies and procedures.

 

 

 

 

These decisions, which were based on the recommendations made by the former Clerk and Engineer, benefited only three members of staff including the former Clerk and Engineer and the former Office and Personnel Manager.

 

 

HR policies and procedures have been reviewed and a new organisational structure for both office-based and Field Staff has been put in place. The remuneration framework has also been reviewed and implemented. Performance appraisal arrangements for all staff are currently being consulted on and will be in place for the New Year

 

 

The arrangements for time off in lieu have been reviewed and will be terminated as from April 2013

Largely achieved. The majority of HR policies & procedures have been updated. A new Employee Handbook will be produced to reflect revised terms and conditions of service following consultation and Board approval in early summer 2013

 

 

Achieved

 

 

 

General Manager

F&SSM

 

 

 

 

 

 

 

 

 

 

F&SSM


 

 

 

Control Objective 1: Services to other Drainage Boards & Private Works

Ref

Weakness identified in PIR

PIR comment

Agreed management action to address weakness

Date

Responsible Officer

247 – 251

 

 

 

 

 

 

 

 

 

 

 

 

 

 

252 - 260

 

 

The Drainage Board provided services to other drainage boards without having considered the strategic implications, costs and risks of doing so.

 

 

 

 

 

 

 

 

 

 

 

 

The Drainage Board’s recording and pricing of private works has not been sufficiently robust and the operation of its ‘profit incentivisation’ scheme was contrary to law.

It was concluded that factors such as risks and rewards, impact and financial cost weren’t adequately considered by the Drainage Board before agreeing to provide services to other internal Drainage Boards.

 

 

 

 

 

 

 

 

 

Internal Drainage Boards may charge the cost of undertaking private works to organisations and individuals for whom they undertake these works. The legislation does not empower an Internal Drainage Board to price the cost of the work it undertakes to generate a profit.

The current arrangements whereby services are provided to other Drainage Boards have been reviewed to ensure they are currently ‘fit for purpose’ and represent VFM. The current arrangements with River Lugg and North Somerset Levels IDBs will terminate at the end of 2013

 

Such arrangements will be further reviewed in the light of the Welsh Government decision on the future of IDBs in Wales

 

 

The arrangements for undertaking ‘private works’ have been reviewed and such work is now restricted to drainage work within the IDD.

 

There is now no profit element in the pricing of such work and the former ‘profit incentivisation scheme’ was discontinued after 2010.

 

Achieved

 

 

 

 

 

 

 

 

 

No decision made by WG as at 04/04/2013

 

 

Achieved

General Manager

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

General Manager

Board Engineer